Dear Mill St. Neighbors:
This is to let you know that the anticipated blasting
schedule for the week of 9/5/17 is as follows:
Tuesday
9/5 and Thursday 9/7, with 2 blasts per day between 8:00 AM and 4:00 PM.
We anticipate that the blasting will be complete by Friday
9/15/17.
Bridge mobilization, previously scheduled to begin 9/4, has
been moved to the week of 9/11/17.
Please feel free to contact me with any questions you may
have.
Sincerely,
Ed
Edward
A. Bouquillon, PhD
Superintendent-Director